Update from Cyden Homes:
Update from Cyden Homes:
We have spoken to the Roads and Sewers (R&S) contractor Daniel Charles (DC’s) for an update on Programme They have finished the Attenuation Basin or Lagoon. The Foul Drainage wet well has been formed and the Pumpstation is the be completed this coming month. The aim is to move away from the boundary with Highfield Road and into the site
Main Programme
· Roads and Sewers (R&S) on site ongoing until early 2026 before Cyden start on plot works
· Phase 1 road only and pumping station on current scope of works
· Off-site works (S278 Works)– Awaiting for approved point of connection from North Power Grid (NPG), info has been submitted to LCC Highways for road space booking for off-site works
· However, we are waiting for HV cable Point of Connection (POC) approval to ensure that the work is collaborative under a Single permit, so as to reduce disruption to existing Ludborough Road (obviously don’t want to do the off-site works and then dig it up again to install the HV cables)
· Drainage connections and water POC will also be under the same scope of works once approved, application for water POC has also been submitted by IUS (Utility service) who are carrying out the on and off site multi utility works.
· DC’s to complete all on-site roads and off-site S278 works
The 278 work will include
· The off-site HV will be installed up to approved POC, water connection to existing Anglian Water main to be made, sewer connections to be made and then S278 works will follow on by DC’s – all under the same permit.
· Anticipating this work to be in January 2026 now because we don’t want to have road closures/traffic management in place over Christmas but this gives us time to get everything in place and reduce disruption.